Unit Prices, Alternates and Allowances on Electrical Tenders: What Each Line on the Bid Form Means

Bid Scout · Wed Nov 11, 2026 · 7:08 AM ET

The base price gets most of the effort, but the bid form usually asks for more numbers, and those extra lines are where shops lose money after award. Here's what each one means on Ontario tenders, with examples from public documents.

Unit prices

A unit price is what you'll charge for one unit of work: one receptacle, one pull station, a set length of conduit and wire. Owners use them to price changes after award.

The Waterloo Catholic District School Board's St Anne Cambridge CES Renovation tender (RFT 2026-11), Addendum 3 is a good example. Its electrical unit prices cover conduit and cable runs at a fixed length, a duplex receptacle including box, cover plate and 5000 mm of conduit and wiring, a 347 V light switch, and a fire alarm pull station. Three details matter:

A lowballed unit price is the rate you'll be stuck with on every change, and deletions come back at less than you priced.

Unit prices can also decide the total. The City of Thunder Bay's Information to Tenderers template says that when an item's amount doesn't match the quantity times the unit price, the unit price governs and the total tender price is corrected. It also says that if you leave an item blank, you're deemed to have covered its cost elsewhere, with no increase to your price. Check your extensions before you submit.

Alternate prices and separate prices

These two get mixed up. The Township of Guelph/Eramosa's signage tender specification package shows the difference on one form:

Both include overhead and profit, bonding, insurance, and permit and inspection fees, but not HST. The form also asks for an electrician's hourly rate, regular and after hours.

Substitutions and suggested alternatives

A substitution isn't an alternate price. It's your offer to use a different product. Thunder Bay's template says that where a product is named, you base your tender on that product, and you can suggest an alternative on a separate statement showing what's specified, what you propose and the change to the tender price. The Guelph/Eramosa form has a similar list for unsolicited substitutions.

A cheaper fixture or panel package goes there, not in your base price.

Cash allowances

A cash allowance is a sum the owner writes into the documents for work whose cost isn't settled yet. Every bidder carries the same figure. Under GC 4.1 of the CCDC 2 – 2020 stipulated price contract:

So carry your markup on allowance work in your base price. Don't add it on top of the allowance.

Watch the tax line too. The St Anne addendum says HST on the cash allowance is not to be included in the tender amount. The Guelph/Eramosa package says the opposite: include HST on the allowances when you fill in the form. Read each form.

The OAA-OGCA recommended supplementary conditions for CCDC 2 – 2020 also let the owner call for competitive bids on allowance work, so don't assume it's yours.

Contingency allowances

A contingency allowance is different. Under CCDC 2 GC 4.2, it covers changes as they come up, it includes your overhead and profit, and it's spent through the normal change order and change directive process. The contract price is then adjusted for whatever wasn't used.

Before you submit

If a tender's own documents say something different from this post, the documents win.