We covered why mandatory site meetings matter, and what the plan-taker list tells you, in Mandatory Site Meetings and Plan-Taker Lists. This post is the practical part: what to do before, during and after the walk so the trip actually improves your electrical price.
Before you leave
- Register as a plan taker first. On bids&tenders pages, the meeting details are often shown only to invited bidders and registered plan takers. York Region's RFT-3850-26, Electrical Substation Maintenance is a current example: the meeting section is gated, though the description gives the date.
- Confirm mandatory or optional. Richmond Hill's site meeting notice, for example on RFQ-2610192, Fire Alarm System Replacement, says bids are accepted only from registered plan takers who signed in before the meeting started and stayed until the end.
- Read the documents before the walk. An LCBO notice for a life safety generator replacement, as summarized on ConstructConnect, asked bidders to review all documents before the meeting. Mark up the electrical drawings with what you want to see: the service, the main distribution, panel locations, risers and tie-in points.
- Plan the route. York's RFT-3850-26 meeting, set for Tuesday, November 17, 2026 at 8:30 AM, visits several facilities, and bidders arrange their own transport between sites. Budget the whole morning.
- Send someone who can price. A runner who signs the sheet keeps you eligible. An estimator or foreman who knows the scope gets you information.
What to bring
- The PPE the documents name. The LCBO notice listed hard hats, safety shoes and high-visibility vests, and said attendees without them may be asked to leave. Richmond Hill puts the onus on attendees to wear the PPE in the bid documents.
- A camera, a measuring tape and notepaper. A Caledon site meeting notice, as summarized on ConstructConnect, encouraged bidders to bring exactly these.
- Your marked-up drawings and a written question list. The LCBO notice asked bidders for a written list of questions to the tender contact.
- Arrive early. Sign-in usually happens before the meeting starts, and late can mean ineligible.
What to record on site
- Your sign-in. Note the time, who signed for your firm, and the buyer's representative.
- Existing electrical gear. Photograph nameplates on the service, switchgear, panels and transformers you'll touch, and note anything that doesn't match the drawings.
- Access and working limits. Ceiling space, room to get equipment in, occupied areas, security escorts, and anything that hints at after-hours or shutdown work.
- Distances and routing. Measure the runs you're unsure of. Note where conduit can and can't go.
- Questions as they come up. Write them down. Don't count on a verbal answer.
- Who else showed up. The other firms in the room are your competition, or the GCs you may sub to.
Why verbal answers don't count
York's RFT-3850-26 notice says no questions will be asked or answered during its site meeting, and all questions go through the portal's "Submit a Question" feature. Thunder Bay's Information to Tenderers template says verbal answers are only binding when confirmed by written addenda. The LCBO notice says verbal responses at site visits are neither official nor binding. Thunder Bay's template also says tenderers can't claim after submitting that they misunderstood site conditions.
So whatever you heard on the walk, put it in writing.
Within 24 hours of the walk
- File your photos and notes with the tender, labelled by area.
- Turn every open item into a written question and submit it well before the question deadline.
- Update your takeoff for anything the site changed: longer runs, extra demolition, temporary power, night work.
- Watch for addenda that answer what came up at the meeting, and acknowledge each one.
- If you're subbing, send your notes and a price to the GCs who were there.
If the buyer's documents and this checklist ever disagree, the documents win.
Sources
- Bid Scout: Mandatory Site Meetings and Plan-Taker Lists (Oct 22, 2026)
- York Region RFT-3850-26, Electrical Substation Maintenance at Various York Region Facilities (bids&tenders)
- City of Richmond Hill RFQ-2610192, Fire Alarm System Replacement (bids&tenders)
- City of Thunder Bay: Information to Tenderers (Section 00100)
- ConstructConnect summary: LCBO Life Safety Generator Replacement, Durham Retail Service Centre
- ConstructConnect summary: Town of Caledon, Creditview Road Sidewalk Upgrades, Streetlight Installation and Site Improvements